How it’s calculated
The brick count uses the same data as the brick calculator: each brick plus its mortar joint fills its nominal face, so modular brick (nominal 8 in × 2⅔ in) needs 6.75 per ft². Materials are bought with a waste allowance; labor is charged on the bricks actually laid.
Example (default example rates): a 20 × 8 ft modular wall = 160 ft² × 6.75 = 1,080 bricks; with 5% waste, 1,134 bricks × $0.90 = $1,020.60. Mortar: ⌈1,134 ÷ 37⌉ = 31 bags × $9 = $279. Labor 1.08 × $700 = $756. Direct cost $2,055.60; +20% = $2,466.72; 7% tax on materials ($1,299.60) = $90.97. TOTAL = $2,557.69 (≈ $15.99/ft² of wall).
Counts and mortar volumes match Brick Industry Association Technical Note 10, Table 4 (running bond, single wythe); patterns with header courses need more brick. Mortar coverage per bag comes from the QUIKRETE data sheet and varies with product, joint size and waste. Labor rates and laying speeds are your own. This is a planning estimate only. It does not include anything not entered above, such as permits, inspections, engineering, site preparation, demolition or disposal (unless entered), access or equipment problems, regional surcharges, contingency or price changes. Get written quotes before committing. For brickwork that includes foundations, ties, flashing, lintels, scaffolding, cleaning and sealing.
Frequently asked questions
How much does bricklaying cost per 1,000 bricks?
It depends on the region, the bond and the detailing, so enter your own rate and compare it with local quotes. This calculator turns a per-1,000 labor rate into a wall price, or you can charge by the hour with your own laying speed.
How many bricks do I need for a wall?
Modular brick needs 6.75 per square foot of wall with 3/8 in joints. Multiply the net area by that and add at least 5% for breakage and cutting. The brick calculator shows the counts for other brick sizes.
Is labor charged on bricks with waste?
No. Bricklayers are paid for the bricks they lay, so labor uses the net count while the brick purchase includes the waste allowance.
How many bricks can a bricklayer lay in a day?
It varies with the wall, bond, bricks and help available, so use your own figure from past jobs for the laying rate. Walls with many openings, corners and cut bricks go slower than long straight runs.
Embed this calculator
Add this free calculator to your own website. Copy the code below into your page’s HTML:
Need this calculator branded, changed or built around your own prices?See custom business solutions →
Sources
- Technical Note 10: Dimensioning and Estimating Brick Masonry (Table 4) — Brick Industry Association
- QUIKRETE Mortar Mix product data sheet (yield per bag) — QUIKRETE Companies
- Masonry Workers: Pay (Occupational Outlook Handbook) — U.S. Bureau of Labor Statistics
Formulas are taken from the free public references above. Results are provided “as is” for informational and educational purposes only. See our disclaimer.
Added · Last updated · How we check our calculators
Spotted a mistake or missing option? Report a problem· Suggest a calculator