Concrete Slab Calculator

How much concrete for a slab, patio or driveway: cubic yards, cubic meters and 40/60/80 lb bags, with waste and ready-mix cost.

4 in (10 cm) is typical for patios and walkways; driveways are often 5–6 in.
%
Allow 5–10% for spillage, uneven subgrade and form deflection.
$per yd³
Enter your local supplier’s price per cubic yard.
Your rate is remembered on this device.

Results

Concrete needed (incl. waste)
1.358
Net slab volume
1.2346
Or 80 lb pre-mix bags
62 bags
Slab area
100
Estimated ready-mix cost
$224.07
Excludes delivery, short-load fees, pumping, rebar and labor.

Estimate only. This tool is for informational and educational purposes. Results depend on your inputs and simplifying assumptions, and are not a substitute for professional engineering, design or financial advice. Always verify with a qualified professional and applicable codes before purchasing, building or making decisions.

How it’s calculated

A slab is a rectangular prism, so its volume is length × width × thickness. We then add your waste allowance.

Volume = L × W × T × (1 + waste%) Cubic yards = cubic feet ÷ 27 Bags = ⌈ volume (ft³) ÷ bag yield (ft³) ⌉

Example: a 10 ft × 10 ft slab, 4 in thick = 10 × 10 × (4/12) = 33.3 ft³ = 1.23 yd³. Add 10% and you need about 1.36 yd³. Ready-mix suppliers usually sell in ¼ or ½ yd³ increments, so round up when ordering.

Bag yields are typical values printed by manufacturers (≈0.60 ft³ for an 80 lb bag). Check the bag you buy.

Frequently asked questions

How thick should a concrete slab be?

About 4 inches (100 mm) for patios, sidewalks and shed floors; 5–6 inches for driveways that carry cars. Heavier loads need an engineered design.

How much concrete do I need for a 10x10 slab?

At 4 in thick: 10 × 10 × (4/12) = 33.3 ft³ = 1.23 yd³. With 10% extra that is about 1.36 yd³ (order 1.5 yd³ of ready-mix), or 62 bags of 80 lb mix.

How many 80 lb bags make a cubic yard?

About 45. A cubic yard is 27 ft³, and an 80 lb bag yields roughly 0.60 ft³, so 27 ÷ 0.6 = 45 bags.

Should I add extra concrete?

Yes. 5–10% extra covers spillage, uneven ground and form bulging. Running short mid-pour causes cold joints.

Embed this calculator

Add this free calculator to your own website. Copy the code below into your page’s HTML:

Sources

Formulas are taken from the free public references above. Results are provided “as is” for informational and educational purposes only. See our disclaimer.

Spotted a mistake or missing option? Report a problem · GitHub issue· Suggest a calculator