How it’s calculated
A three-point estimate asks for an optimistic time a, a most likely time m and a pessimistic time b for each task. PERT (Program Evaluation and Review Technique) treats each task time as a beta distribution and uses simple formulas for its mean and standard deviation. Along the critical path (tasks done one after another) the means add up and so do the variances, and the total is taken to be roughly normal, which gives the chance of meeting a target date.
The assumptions are the standard PERT ones: tasks are independent, there are enough tasks on the critical path for the central limit theorem to apply, and tasks off the critical path are ignored. The triangular option weights the three points equally, which gives a larger mean when the pessimistic tail is long.
Worked example (IIT / NPTEL Project Planning, PERT example): the critical path has four activities with (a, m, b) = (2, 4, 8), (6, 6, 6), (3, 6, 9) and (8, 16, 20) days. Their means are 4.33, 6, 6 and 15.33, so the project is expected to take 31.67 days, and their variances 1, 0, 1 and 4 add to 6, an SD of 2.449 days. The chance of finishing within 36 days is Φ((36 − 31.67)/2.449) = Φ(1.77) = 0.9616.
Frequently asked questions
What do optimistic, most likely and pessimistic mean?
Optimistic is how long the task takes if everything goes right, pessimistic if most things go wrong (but not a catastrophe), and most likely is the usual case. All three must be in the same time unit.
Why do variances add and not standard deviations?
For independent tasks the variance of a sum is the sum of the variances. Standard deviations add only when every task overruns together, which would make the total SD larger.
PERT or triangular?
PERT puts four times as much weight on the most likely value, so its mean stays close to m. The triangular mean weights all three points equally, so it reacts more to a long pessimistic tail. Both are approximations; the triangular SD is usually larger.
Which tasks should I list?
For a single total, list the tasks on the critical path, the longest chain of tasks that must happen one after another. Tasks done in parallel off that path are ignored by classic PERT, which can make the result optimistic.
Embed this calculator
Add this free calculator to your own website. Copy the code below into your page’s HTML:
Need this calculator branded, changed or built around your own prices?See custom business solutions →
Sources
- Project Planning: PERT time estimates, example and probability statements (NPTEL, IIT) — NPTEL (Indian Institutes of Technology)
- Project Planning: PERT example, activity time estimates, means and variances (NPTEL, IIT) — NPTEL (Indian Institutes of Technology)
- Project Planning: probability of meeting a target date (NPTEL, IIT) — NPTEL (Indian Institutes of Technology)
- Project Planning: standard PERT assumptions (NPTEL, IIT) — NPTEL (Indian Institutes of Technology)
- NASA Cost Estimating Handbook v4.0, Appendix G: Cost Risk and Uncertainty Methodologies (triangular three-point inputs, central limit theorem for totals) — NASA
- Probability, Mathematical Statistics, and Stochastic Processes (Siegrist), §5.24 The Triangle Distribution — LibreTexts
Formulas are taken from the free public references above. Results are provided “as is” for informational and educational purposes only. See our disclaimer.
Added · Last updated · How we check our calculators
Spotted a mistake or missing option? Report a problem· Suggest a calculator