Render Calculator

How many bags of premixed render, stucco or plaster you need for a wall from its area, thickness, number of coats and bag yield, with waste and cost.

Subtract doors and windows. Length × height of each wall, added together.
3/16 in (about 5 mm) per coat gives the 3/8 in (9.5 mm) total in the manufacturer’s example. Check the data sheet for your product and substrate.
Volume of mixed render one bag makes. QUIKRETE Scratch and Brown Base Coat Stucco 1139 (80 lb / 36.2 kg bag) yields about 0.75 ft³ (21 L). Replace it with the figure on your own product’s data sheet.
%
Allow for rebound, uneven walls and mix left in the bucket. Manufacturers’ coverage figures are “approximate and vary with thickness, waste, etc.”
$per bag
Your rate is remembered on this device.

Results

Bags needed (incl. waste)
19 bags
Wet render needed (incl. waste)
13.75
Wet render in place (before waste)
12.5
Total thickness
0.38
Estimated render cost
$285.00
Bags only: excludes lath, bead, primer or bonding agent, finish coat, scaffolding and labor.

How it’s calculated

Render, stucco and plaster are applied as a layer, so the wet volume you need is wall area × total thickness. Divide by the volume one bag makes and round up.

Total thickness = thickness per coat × coats Wet volume = wall area × total thickness × (1 + waste%) Bags = ⌈ wet volume ÷ wet yield per bag ⌉

Example: 400 ft² of wall at 3/16 in per coat, 2 coats: total thickness 3/8 in = 0.03125 ft. 400 × 0.03125 = 12.5 ft³. With 10% waste, 13.75 ft³. At 0.75 ft³ per bag that is 18.3, so 19 bags. This agrees with the data sheet’s coverage of 20–24 ft² per bag at 3/8 in (400 ÷ 22 ≈ 18 bags before waste).

This calculator is for premixed bagged render, where the bag already contains cement and sand and you only add water, so you don’t need a dry-mix volume or a sand-to-cement ratio. If you mix render from separate cement and sand, the dry materials take up noticeably more volume than the wet mix they produce, and a different calculation applies.

Thickness varies with the substrate and the number of coats (a scratch coat, brown coat and finish coat are separate layers), so follow your product’s data sheet and local building code.

Frequently asked questions

How many bags of render do I need per square meter?

About 0.45 to 0.55 bags of an 80 lb (36 kg) premix per square meter at 3/8 in (9.5 mm) thickness, using the manufacturer’s coverage of 1.8–2.2 m² per bag. Thicker coats need proportionally more.

How thick should render be?

It depends on the product and the number of coats. The example data sheet gives coverage at 3/8, 1/2 and 3/4 in (9.5, 13 and 19 mm). Always follow your manufacturer’s instructions.

Do I need extra for waste?

Yes. 10% is a sensible start, more on rough masonry, for spray application or if you are inexperienced.

Is stucco the same as render?

In the US the cement-based wall coating is called stucco and in Australia, the UK and elsewhere it is called render. The calculation is the same.

Embed this calculator

Add this free calculator to your own website. Copy the code below into your page’s HTML:

Need this calculator branded, changed or built around your own prices?See custom business solutions →

Sources

Formulas are taken from the free public references above. Results are provided “as is” for informational and educational purposes only. See our disclaimer.