How it’s calculated
The economic order quantity (EOQ) is the order size that makes the total of two yearly costs as small as possible: ordering (more, smaller orders cost more) and holding (larger orders mean more stock sitting around). At the best size the two are equal.
D is annual demand, S the cost per order and H the holding cost per unit per year. The model assumes steady demand, orders that arrive all at once and no stockouts.
Example (University of Kentucky inventory notes, worked example): demand 60,000 a year, $25 per order, $3 holding cost per unit: EOQ = √(2 × 60,000 × 25 ÷ 3) = 1,000 units, 60 orders a year, total cost $3,000. With 240 selling days, daily demand is 250, so with a 3-day lead time the reorder point is 750 units.
Frequently asked questions
How do I work out my holding cost?
Add up what it costs to keep one unit for a year: storage space, insurance, shrinkage or spoilage, and the interest on the cash tied up in stock. Many businesses use a percentage of unit cost, which is why you can enter it that way.
Should I order exactly the EOQ?
Treat it as a starting point. Round to pack or pallet sizes, and check supplier discounts and storage space. The total cost is fairly flat near the optimum, so small adjustments cost little.
What is safety stock?
Extra stock you keep as a buffer against late deliveries or unexpectedly high demand. This calculator adds the amount you enter to the reorder point; it does not work out a safe level for you.
What if my lead time is longer than the time between orders?
Then an earlier order is still on its way when you place the next one, so the stock on hand at which to reorder is lower. The calculator shows that level in the note under the reorder point.
Embed this calculator
Add this free calculator to your own website. Copy the code below into your page’s HTML:
Need this calculator branded, changed or built around your own prices?See custom business solutions →
Sources
- Inventory Models for Certain Demand: Economic Order Quantity (EOQ) — LibreTexts (Northeast Wisconsin Technical College)
- Inventory Management (worked example with reorder point) — University of Kentucky
- Principles of Finance, Ch. 19 Key Terms (ordering costs and carrying costs) — OpenStax
Formulas are taken from the free public references above. Results are provided “as is” for informational and educational purposes only. See our disclaimer.